This article is for Tempo for Cloud.
|
Question |
I can't seem to find a place in the new Jira work item view to edit the Remaining Estimate. |
|---|---|
|
Answer |
Currently, the remaining estimate can be edited in the new Jira work item view if the Time tracking provider is set to Jira. When Tempo is set to be the Time tracking provider, the only way to edit the remaining estimate of a work item is to either log time on it or edit an existing worklog. In the Log Time or Edit Worklog pop-up window, you will be able to enter a new value for the Remaining estimate field. If this is not possible, you would have to change it back to the old work item view and edit the Remaining Estimate through editing the work item, given that the "Time Tracking" Field is added to the "Edit work item" screen. |