Time Tracking Report

The Time Tracking Report displays various time-related information to notice the estimated time versus the actual time spent per issue.

Note: There is no access to worklogs from this report page.

You can also add most of these time tracking columns to other reports, like the Timesheet report. Add them as Additional Fields in the report settings and filters section.

time_tracking_callouts.png

Element

Description

Details

A

Previous and Next icons

Select to scroll to the previous or next week.

B

Time display dropdown

Select to display the day, week, or month.

C

Worked Hours dropdown

Select to display the daily, weekly, or monthly worked hours.

D

Original Estimate column

Displays the initial estimated time specified in the issue field.

E

Est. Time Remaining column

Displays the current estimation in the Estimate field. The estimation is reduced when work is logged on an issue and may be increased if more work is needed.

F

Time Spent column

Displays the sum of worklogs for an issue, during the period selected. Note: There is also a Jira issue Timespent field, which is the overall value of time logged for an issue.

G

Variance column

Displays the time variance, calculated as Original Estimate - Estimate (Time Spent + Est. Time Remaining).

H

Original Estimate Remaining column

Displays the calculation of the Original Estimate - Time Spent.

I

Progress Column

Displays a progress bar to visualize the progress per issue. Calculated as Time Spent / ( Est. Time Remaining + Time Spent). Displays as 100% when Est. Time Remaining is 0.

J

Total row

Displays the total time per time column and the total progress for the displayed table.