Scheduling Precedence
By default, tasks in Gantt are automatically scheduled based on the project start date, work estimates and dependencies. If Manual Scheduling is selected in the Gantt configuration, tasks will be scheduled in the following manner, depending on the Manual Scheduling options:
Use sprints for manual scheduling AND Prefer sprints over manual start and finish dates are selected:
If a work item is assigned to a sprint, it will be scheduled for the duration of that sprint, even if it has Start/Finish dates available
If a work item is not assigned to a sprint, it will be scheduled based on its Start/Finish dates
If no Start/Finish dates are available, the work item is resolved and Use Resolution Date as the Finish Date is selected, the work item will be scheduled based on its resolution date
Otherwise, the work item will be automatically scheduled
Use sprints for manual scheduling is selected, but Prefer sprints over manual start and finish date is NOT selected:
If a Start or Finish date is available, the work item will be scheduled based on these, even if it is assigned to a sprint
If no Start or Finish date is available, but the work item is assigned to a sprint, the work item will be scheduled for the duration of that sprint
If the work item is not assigned to a sprint, is resolved and Use Resolution Date as the Finish Date is selected, the work item will be scheduled based on its resolution date
Otherwise, the work item will be automatically scheduled
Use sprints for manual scheduling is NOT selected:
If a Start or Finish date is available, the work item will be manually scheduled based on these
If no Start/Finish dates are available, the work item is resolved and Use Resolution Date as the Finish Date is selected, the work item will be scheduled based on its resolution date
Otherwise, the work item will be automatically scheduled