Creating a Gantt Chart
To open or create a Gantt chart, select Gantt from the Structure menu. Your Gantt chart will appear beside the current structure.
To close the Gantt chart, select Main.
Default Settings
If this is the first time you’ve added a Gantt chart to the structure, the chart will be pre-configured using the following settings:
The Project Start day is set to the current date
Tasks are automatically scheduled based on Time Tracking
Standard calendar is selected
The fiscal year begins in January
To change any of these settings or add additional customization to your Gantt chart, click the Settings button (gear icon) in the Gantt toolbar.
Not seeing your Gantt chart?
Have you installed both Structure and Gantt Charts for Structure?
Do you have at least "Browse Users and Groups" Global Permission in Jira?
If not, please speak with your Jira administrator.