Access Privileges for Planned vs Actual Report
Access to the Planned vs Actual report is controlled by two team permissions: View Team Plans and View Team Worklogs. You need to have both of these permissions for a team to access the report. Your Tempo Team Administrator can grant you these permissions.
Example:
If you have the permission to view worklogs and plans for teams A and B, but only permission to view worklogs for team C, you can view the Planned vs Actual report showing planned and logged hours for teams A and B, but not team C.
View worklogs and View plans permission on the team level are managed on the team's Permissions page.
![](../../__attachments/3389988271/2020-06-11_16-48-44%20(1).png?inst-v=4f633ce0-1102-4b14-82de-92bf3477a27e)
In this example the planned vs actual hours for this team will be visible to the Team Lead, but the Member role will not have access to this information.