Timesheets, Planner, Cost Tracker Release Notes
2024-09-18
Tempo Global Permissions - Changes to Tempo Financial Manager permissions
The Tempo Financial Manager Access global permission has been renamed to Tempo Project Manager. This change only impacts the permission's name and does not affect any current users or groups who are granted it. No other changes to the permission have been made, and you should continue to use this to grant your users access to Tempo Financial Manager.
Added two new permissions that are currently inactive:
Tempo Project Administrator - By default, Jira Administrators are granted this permission. This will allow users to manage all projects, including global project settings.
Tempo Project Viewer - This will allow a user to have limited access to projects that have been shared with them.
2024-09-16
Fixed: The Remaining Estimate in the Tempo Sidebar in the Jira issue view was not always up-to-date with Jira's own Remaining Estimate value.
2024-09-04
Timesheets and Portfolio Manager Integration
If you leverage Portfolio Manager for capacity planning, schedule forecasting, and scenario modeling in your Jira projects, you can now pull Timesheets worklog data into Portfolio Manager.
Portfolio Manager uses Timesheets worklogs to provide up-to-date reports and forecasts, with time tracking automatically adjusting remaining estimates that are then used for schedule forecasting.
2024-09-02
Fixed: A permission check error was displayed when generating the Labor Costs CSV export.
2024-08-29
Fixed: Timesheet approval comments were cut off inside the column.
2024-08-27
Fixed: You couldn’t bulk add members with
&
in the group name.
2024-08-23
Fixed: The Basic calendar mode in My Work only displayed up to 250 calendar events per week.
2024-08-21
Reporting
You can now group by a checkbox type Jira custom field. The first value returned by the Jira API is used to group the data.
Other improvements
Fixed: When you created a multi-period plan, the Capacity report didn’t display the planned time correctly.
Fixed: When a plan extended into the next period, the planned hours in the Capacity report and Planned Time report didn’t match.
2024-08-16
Fixed: Couldn’t open a user's timesheet in a new tab in approvals.
2024-08-15
Reporting - Raw data export changes
The following changes have been made to the Logged Time Report raw data export, which impacts people who use column order, index number, or column name to fetch data. These changes help address reporting accuracy, especially when rounding from seconds to hours.
Hours
has been renamed toLogged Hours
.Billed Hours
has been renamed toBillable Hours
.Issue Original Estimate
has been renamed toIssue Original Estimate Hours
.Issue Remaining Estimate
has been renamed toIssue Remaining Estimate Hours
.A new column,
Logged Seconds
, has been added adjacent to theLogged Hours
/Hours
column.A new column,
Billable Seconds
, has been added adjacent to theBillable Hours
/Billed Hours
column.A new column,
Issue Original Estimate Seconds
, has been added adjacent to theIssue Original Estimate
/Issue Remaining Estimate Hours
column.A new column,
Issue Remaining Estimate Seconds
, has been added adjacent to theIssue Remaining Estimate
/Issue Remaining Estimate Hours
column.
If you download your raw report data to Excel, the following changes also occur in the Logged Time Report’s Users tab.
Worked
has been renamed toLogged Hours
.Billed
has been renamed toBillable Hours
.Planned
has been renamed toPlanned Hours
.Required
has been renamed toRequired Hours
.A new column,
Logged Seconds
, has been added adjacent to theWorked
/Logged Hours
column.A new column,
Billable Seconds
, has been added adjacent to theBilled
/Billable Hours
column.A new column,
Planned Seconds
, has been added adjacent to thePlanned
/Planned Hours
column.A new column,
Required Seconds
, has been added adjacent to theRequired
/Required Hours
column.
2024-08-01
Fixed: In some cases, the group by option was incorrect in Mozilla Firefox.