Filter by Resource

To view only work items assigned to a specific resource:

  1. Open the Resources panel

  2. Highlight the resource's name

  3. Select the Filter button

Filter the Gantt chart by a resource

When you filter by resource:

  • Work items assigned to that resource will be visible in the WBS and Gantt chart

  • Work items above those in the hierarchy will be visible 

  • All other work items will be hidden

Milestones and groups are not assigned to resources in Gantt, so these items may be hidden even if they are "assigned" to the specified resource in Structure.

Filter by Multiple Resources

To filter by more than one resource, select the small squares to the left of each resource, and then click the Filter button.