Gantt Charts for Structure (Cloud)

Jira-based Baselines

Jira-based baselines allow you to compare the current task timelines to timelines found in a Jira custom field. This allows you to compare the current chart to a previously planned schedule, alternate schedule, transition dates, or any other date/time data available in Jira.

image-20261030-173803.png

Creating a Jira-based Baseline

You must be the structure owner, or have edit permissions for the structure, to create a baseline.

To create a new baseline:

  1. Open the Baseline menu in the Gantt toolbar and select Create New.

    cdn?allowAnimated=true&client=72d4b759-df8c-4a5a-810a-830f5652e60f&collection=contentId-3676768043&height=125&max-age=2592000&mode=full-fit&source=mediaCard&token=eyJhbGciOiJIUzI1NiJ9.eyJpc3MiOiI3MmQ0Yjc1OS1kZjhjLTRhNWEtODEwYS04MzBmNTY1MmU2MGYiLCJhY2Nlc3M
  2. Give the baseline a name and select Jira-based baseline from the Type dropdown.

    image-20261030-173223.png
  3. Enter the following information:

    • Start Date: The custom field you want to use as the Start Date for your baseline’s tasks.

    • Finish Date: The custom field you want to use as the Finish Date for your baseline’s tasks.

    • Treat task with only Start Date value as a milestone: When turned on, tasks with only a Start Date value will display as milestones in the baseline.

    • Treat task with only Finish Date value as a milestone - When turned on, tasks with only a Finish Date value will display as milestones in the baseline.

      image-20261030-173042.png

For more precise placement in a chart, use Date Time fields instead of Date fields.

  1. Select Create.

Viewing a Baseline

After you create or select a baseline, any tasks with start and finish dates display as a solid grey bar behind your tasks. If you selected either of the milestone options, any work item with only one date displays a milestone baseline. Tasks with no dates, or only one date that doesn’t match the milestone dates, will not have a baseline in the Gantt chart.

You can also use baseline dates as a data source for columns within Structure, or as a variable in formulas. This can help you view and compare your baselines without the need to open the full Gantt view.