Pie Chart Report

The Pie Chart report for Jira Server and Data Center displays a visual summary of worked time for a project in a certain period.

pie_chart_server_callouts.png

Element

What is it?

What can I do with it?

A

Pie Chart

Displays the issues for the selected period. Wedges are sized according to the percentage of time worked. Click any issue number to access the full issue.

B

Previous and Next icons

Click to scroll to the previous or next week.

C

Worked Hours icon

Select whether to display the daily, weekly, or monthly worked hours.

D

Issue list

Displays the list of issue for the time period selected. Click any issue number to access the full issue.

E

Total row

Displays the total time spent for the issues in the time period selected.