Tempo Loop

Editing Items in a Scenario

As you plan your scenario, you may need to update field values for an item. You can make those changes just like you would in the Portfolio or the Active Plan.

The edits you make in Scenario Modeling remain within the scenario (and have no effect on your Portfolio, Active Plan, or Integrated services) unless you activate the scenario.

Editable Fields

The following fields can be edited in Scenario Modeling:

  • Team

  • Effort Estimate

  • Status

  • Earliest Start Date

  • Deadline

  • Dependencies

All other fields (Name, Item Type, dates, financials) are read-only in a scenario. To make changes to these fields, use Portfolio or the Active Plan.

Inline Editing

Scenario Modeling supports inline editing for the following fields:

  • Team: choose from teams assigned to the portfolio and teams not associated with any portfolio

  • Effort Estimate: estimates are grouped by scheme with time range hints

  • Status: the item’s position in the workflow

Editing item fields in Planner.gif

Editing in the Item Panel

Clicking an item’s name opens the Item panel, where you can view additional information about the item. From the Item Panel, you can edit the item’s Team, Effort Estimate, Status, Earliest Start Date, Deadline, and dependencies.

Item Panel in Planner.jpg

The Dependencies tab lists dependencies for the current item, as well as dependencies inherited from its ancestors (parent item, etc.). Inherited dependencies are read-only.

Bulk Editing

In the Table view, select the checkboxes next to each item you want to edit. As soon as more than one item is selected, the bulk edit bar appears at the top of the Items Table.

Bulk edit panel in Planner.jpg

Once you’ve made the desired changes, click Apply.

To select a range of work items, press Shift and click.

Publishing Changes

Changes you make in a scenario are not reflected in the portfolio or your integrations until you activate the scenario.

To activate a scenario, click the Activate Scenario & publish button.

Publish options in Planner.jpg

You have two publish options:

  • Publish to Portfolio - updates changes in your Portfolio. This will not overwrite any data in your integrated platforms. You can push these changes later using the Sync with Integrations option in Portfolio, but if you pull items from your integration first, you might lose these changes.

  • Publish to Portfolio & integrations - overwrite existing data in the Portfolio and your integrated platforms.

Synced Fields

When you publish a scenario, the following fields are updated to match the scenario values:

  • Status

  • Effort Estimate

  • Team

  • Deadline

  • Earliest Start

  • Scheduling Priority

  • Start Date - updated to match the scenario’s Forecasted Start date

  • End Date - updated to match the scenario’s Forecasted Finish date

Activating a scenario overwrites existing values in the Portfolio and integrated platforms. These changes cannot be undone.

Activating a scenario isn’t the end! You can return to the scenario, update it, and reactivate it at any time.

Publishing Changes to Individual Items

If you’re not ready to publish an entire plan, but need to push small changes back to your portfolio, you can publish changes to individual items in Planner.

To do so:

  1. Click the item’s name to open the Item Panel

  2. In the integration section, open the dropdown and select Publish

Publishing changes to a single item.jpg