This article is for Tempo for Cloud.
Scope: Tempo Capacity Planner (Cloud) with "Sync Plans with Jira Work Items" enabled. Covers ways to check why plans are not syncing between Capacity Planner and Jira.
Quick reference: how a sync works
Sync is two-way and applies only to the four attributes mapped to Jira fields: plan start date, plan end date, total planned time and assignee. A plan is created automatically only when all four mapped fields have a value. Plans do not back-fill for work items that existed before sync was enabled.
Method 1: Confirm the feature is on and who can change it
-
Check that Sync Plans with Jira Work Items is enabled on the instance. Enabling it requires the Jira Administrator permission.
-
Check that the user setting up the sync has the Edit Work Items permission in the Jira space. Without it, the field mapping cannot be configured.
-
Check that the user editing a synced plan has Edit Work Items permission on the work item. A synced plan follows Jira permissions, not the Tempo "Manage plans" permission.
Method 2: Compare the mapped fields with the Jira work item view
-
Open the Sync drop-downs in Capacity Planner and note the field chosen for each attribute.
-
Open the Jira space's work item view (Space settings > Work Items Layout) and confirm the same fields are shown there.
-
Check data types. Plan start and end must map to Jira date fields. Total planned time must map to a number field, or to the default Original Estimate field.
-
For Team plans, confirm Assignee is the Tempo Team custom field. Team plans will not stay synced otherwise.
Method 3: Check the work item's status and history
-
Confirm the work item is not in a "Done" status (Closed, Resolved, etc.). Done items are excluded from sync.
-
If the item was closed before sync was enabled, reopen it. Then check whether a plan appears.
-
If the item was closed after sync was enabled, edits made after the close are not synced. Reopen the item to resume sync.
Method 4: Check whether the work item has all four mapped fields
-
Open the work item in Jira and confirm start date, end date, total planned time (Original Estimate by default) and assignee all have values.
-
If any value is missing, add it. A plan is created automatically once all four are filled.
-
For older items with all four fields already filled, clear one field, save, then re-enter the value. This triggers plan creation.
-
Alternatively, create the plan manually in Capacity Planner.
Method 5: Check the time units of total planned time
-
Jira displays the synced number field in seconds. Capacity Planner displays the same value in hours.
-
If the value entered in Jira is below 60, Capacity Planner may show no planned time. Enter at least 60.
-
Tempo recommends Original Estimate for this mapping. Do not use Remaining estimate, because it changes as time is logged and can drop to zero.
Method 6: Check for synced-plan behaviour that looks like a sync failure
-
Synced plans cannot be recurring plans.
-
Only one synced allocation is allowed per work item. Additional plans on the same item must be unsynced.
-
Plans can only be created for work items and Jira users. Plans for generic resources or spaces are unsynced by design.
-
Synced plans are deleted automatically if the work item is deleted, or if a synced field is cleared. If iteration cycles or story points are enabled, disable those fallbacks to get this behaviour.
-
Sub-tasks are separate work items. A sub-task has its own synced plan, separate from its parent story.
-
If the plan was saved with "Sync this plan with Jira work item" cleared, it is an unsynced plan. Changes made in Capacity Planner will not update Jira.
Method 7: Check the feature state and app health
-
If the sync option is missing or the plan form shows a "Jira feature is switched OFF" message, a Jira admin must enable Sync Plans with Jira Work Items in the Tempo Planning Time settings.
-
If Capacity Planner does not load and shows "Something went wrong on our end", check Jira settings > Marketplace Apps for Tempo Core. Reinstall Tempo Core if it is missing or broken. If that does not help, reinstall all Tempo apps (data is not affected).
Method 8: Use the classic planning screen to isolate the problem
-
Clear "Sync this plan with Jira work item" on a test plan and save it.
-
If the plan saves, the problem is in the sync mapping or field values, not in plan creation.
-
If the plan does not save, check permissions and the Planning Time settings before going further.
Checklist before escalating
-
Sync enabled, and the setup user has Jira Administrator and Edit Work Items.
-
Mapped Jira fields match the work item view and have the right data types.
-
Work item is not Done, and all four mapped fields have values.
-
Total planned time is entered in a unit that gives at least 60 seconds.
-
Team plans use the Tempo Team field for Assignee.
-
Tempo Core is installed and Capacity Planner loads without error.
-
Test on one work item and note the work item key, plan ID, the mapped fields and any error text.
If the checklist passes and sync still fails, raise a support request with the details above. If the docs are missing or wrong for the case, raise a PE document request (doc-gap).