Gantt Fields in Structure
Once you've created a Gantt chart, you can view and utilize its fields within the corresponding structure by adding them as columns.
To see all the available Gantt fields and their meanings, see List of Gantt Fields Available in Structure.
Adding a Gantt Field Column to a Structure
To add a Gantt field to your structure, click the + icon to the right of the column headers to create a new column in the structure. Select Gantt fields from the list, and choose the field you want to add.
Copying Gantt Values to Jira
Gantt field values are only available in Gantt and Structure; however, it is possible to write Gantt values to Jira fields, using Copy to Jira. This way, these values can be viewed and utilized by anyone, whether they have access to Structure or not.
To copy Gantt values to Jira:
Select the Copy to Jira button in the Gantt toolbar.
Choose your From (Gantt field) and To (Jira field) values. Gantt Start Date and Finish Date are selected by default, but you can change these and/or add additional fields as necessary.
Select Start Copying.