The remaining estimate does not update when changing the original estimate

Problem

The remaining estimate does not update if you change the original estimate after time has been logged on the issue.

Solution

While Tempo may change the appearance of the time tracking fields, the functionality is maintained by Jira. This is the intended behaviour if you change the Original estimate after time is logged.

For additional information, please see:

https://support.atlassian.com/jira/kb/time-remaining-not-updating-after-changing-original-estimate-in-jira-cloud/