This article is for Gantt Charts Cloud.
Question
The work on some of the tasks on my charts has not started. The project date of my chart was set a while ago, and these tasks remain in the past. I would like to ensure that these tasks are always scheduled to start today, until the actual work on them begins.
Answer
You can achieve this in multiple ways:
-
Adjust the project start date daily. This will move all automatically scheduled tasks to start on a specific date.
-
Use a Slice configuration for all such tasks. For example, you can include all open tasks that are not yet ‘in progress’: https://help.tempo.io/gantt/latest/slice-based-configurations and set their Start Date as the Formula option. And use the today() formula. As a result, the Start date of these tasks will be automatically changed every day. And once a task reaches the ‘in progress’ state, it will be excluded from the Slice’s scope.